Project Overview

Crushing & Screening Plant (Sandvik) - NEC Contract

Managed procurement, construction and commissioning of the Crushing and Screening Plant, maximising ore processing capabilities and operational efficiency.

The Challenge

Delivering a Sandvik crushing and screening plant from procurement through to commissioning.

Our Solution

Integrated EPCM-style delivery under NEC contract terms.

The Outcome

Achieved 290,000 LTI-free hours, closely approaching the targeted goal of 300,000 hours.

Project Details

Client
Shanta Gold
Location
New Luika Gold Mine, Tanzania
Sector
Mining
Disciplines
mechanical structural piping electrical
Project Period
Apr 2014 – Feb 2015